By Henry McClure, MCRE Media | Nov. 16, 2026
Picture a 4½-acre crystal-blue lagoon with a hotel, apartments, a tiki bar, a zipline and waterfront restaurants. Kansas taxpayers were told it would rise in Derby, just south of Wichita. Four years after the state signed off and $35,285,000 in sales-tax-backed STAR bonds were sold, the site has no buildings above ground. Now the Kansas Department of Commerce has taken the developer to court.
On Nov. 2, Commerce sued in Sedgwick County District Court. "More than four years after the project was approved and bonds were sold, it has not been built," the state says in its filing, as quoted by The Wichita Eagle. "Announced opening dates have come and gone."
Who is being sued? According to the Eagle's reporting, the defendants are:
None of the reports I found say Worner, Murfin or Steven are sued personally. They are identified as the people behind the company. The state is also not asking for damages from anyone. It wants a court order on the bond money. That points to a case aimed at the company and the escrow account, not at anyone's personal bank account. The case number and the petition's caption had not been published in any coverage I found as of today, so that last point stays open until the court file is pulled.
What the state wants:
The state is careful about what it is not asking for. The suit says Commerce "is not seeking to end the Derby STAR Bond District, cancel Derby's agreements, or stop the developer or anyone else from building with private funds." It isn't seeking repayment of money "already legitimately spent on eligible project expenses," and it isn't blocking the developer from asking for approval again.
Kansas' STAR Bonds Financing Act says construction has to begin within two years after a project plan is adopted. If it doesn't, according to the statute as quoted in the suit, "funding for such project shall cease."
Derby adopted the Derby Shores plan on May 10, 2022, and the bonds sold in July 2022. The developer's lawyers say construction started in January 2023, when a barn and a farmhouse were torn down. The state says that doesn't count, and it uses the city's own paperwork to make the point: "The City's own 2026 report to the State says construction began in 2026." The suit says there is no vertical construction and that "ground cleared in the past has gone back to weeds."
Tearing down a barn is not building a resort. If a barn demolition can start the two-year clock, the deadline means nothing. That's the question a judge will now decide.
Commerce had already ordered draw approvals stopped before it filed. According to the suit, Derby asked the state to rescind that order, and the developers asked the city to start paying again.
The city's own numbers, posted Nov. 13:
The announced price tag grew from $130 million to $160 million after Steven, who founded Genesis Health Clubs, came on in 2024 as "component developer" and doubled the lagoon to 4½ acres. "I didn't think it would be enough of a draw," he told the Eagle that year.
Derby says its STAR district is "performing well," its bonds "are not at risk of default," and annual audits have found no problems with how proceeds were paid out. That may all be true. It doesn't answer the basic question: what did $9.25 million in public money buy, and why is a lagoon promised for 2024 still a field?
Some readers may know him as "Rick Warner," but state and city records spell it Worner. He is the Leawood-area dealmaker (National Realty Advisors) behind Derby's STAR district, and his track record deserves a look.
Worner also says he helped spearhead Kansas Speedway, Village West and Schlitterbahn. I could not independently confirm his role in those.
Worner has not been charged with any crime. I found no bankruptcy, lien or bond default tied to him. None of the developers returned the Eagle's calls.
STAR bonds aren't a Derby problem. They're a Kansas problem. The sales tax that pays them off "would otherwise go to the State General Fund," as Commerce's own suit says. "Kansas taxpayers carry most of that cost." That's your money, whether you live in Derby, Garden City or Topeka.
In 2021, the Legislative Post Audit found only 3 of 16 STAR attractions met Commerce's tourism goals. The Legislature extended the program this year anyway. Topeka has its own STAR history: the state's database lists $10.4 million for Heartland Park.
There's one more lesson for Topeka. Whether it's STAR bonds in Derby or the TIF, CID and consultant deals at Topeka City Hall, the pattern is the same: big promises, public money out the door, and the public told to trust the paperwork. I credit Commerce for finally enforcing a deadline the Legislature wrote. Every city council in Kansas should be asking the same thing: what did the public get for the money, and when?
Rick Worner, Dave Murfin, Rodney Steven II and the City of Derby are welcome to respond, and I'll run it.
Sources: The Wichita Eagle, Nov. 12, 2026 (kansas.com/news/business/biz-columns-blogs/carrie-rengers/article318035193.html); KAKE, Nov. 13, 2026; KWCH, Nov. 13, 2026; City of Derby update, Nov. 13, 2026 (derbyks.gov/m/newsflash/Home/Detail/2842); Kansas Commerce STAR bond transparency database; Wichita Eagle, Apr. 4, 2017 (GoodSports suit); U.S. District Court for Kansas, Wichita Destination Developers v. Focus Hospitality Services, No. 18-2345-KHV (Feb. 5, 2019); The Sentinel, Oct. 31, 2019; Kansas Legislative Post Audit, Aug. 2021.
Henry McClure, MCRE Media | (762) 291-2765
Source: @KCStar posts since yesterday morning.
---------- Forwarded message --------- From: Team Bowes < Bowes@teambowes.com > Date: Wed, Nov 18, 2...