Four Years, $35 Million in Bonds, No Lagoon: The State Sues Over Derby Shores

By Henry McClure, MCRE Media | Nov. 16, 2026

Picture a 4½-acre crystal-blue lagoon with a hotel, apartments, a tiki bar, a zipline and waterfront restaurants. Kansas taxpayers were told it would rise in Derby, just south of Wichita. Four years after the state signed off and $35,285,000 in sales-tax-backed STAR bonds were sold, the site has no buildings above ground. Now the Kansas Department of Commerce has taken the developer to court.

The lawsuit

On Nov. 2, Commerce sued in Sedgwick County District Court. "More than four years after the project was approved and bonds were sold, it has not been built," the state says in its filing, as quoted by The Wichita Eagle. "Announced opening dates have come and gone."

Who is being sued? According to the Eagle's reporting, the defendants are:

  • Derby Destination Development, LLC, the master developer. The Eagle describes it as a team made up of Dave Murfin, Rick Worner and Rodney Steven II.
  • Security Bank of Kansas City, the bond trustee holding the money.
  • The City of Derby, which issued the bonds.

None of the reports I found say Worner, Murfin or Steven are sued personally. They are identified as the people behind the company. The state is also not asking for damages from anyone. It wants a court order on the bond money. That points to a case aimed at the company and the escrow account, not at anyone's personal bank account. The case number and the petition's caption had not been published in any coverage I found as of today, so that last point stays open until the court file is pulled.

What the state wants:

  • A temporary, and possibly permanent, injunction stopping any more bond money from going to the project.
  • A full accounting of the money spent so far.
  • If the law's requirements aren't met, the unspent proceeds applied to paying off the bonds.

The state is careful about what it is not asking for. The suit says Commerce "is not seeking to end the Derby STAR Bond District, cancel Derby's agreements, or stop the developer or anyone else from building with private funds." It isn't seeking repayment of money "already legitimately spent on eligible project expenses," and it isn't blocking the developer from asking for approval again.

The two-year rule

Kansas' STAR Bonds Financing Act says construction has to begin within two years after a project plan is adopted. If it doesn't, according to the statute as quoted in the suit, "funding for such project shall cease."

Derby adopted the Derby Shores plan on May 10, 2022, and the bonds sold in July 2022. The developer's lawyers say construction started in January 2023, when a barn and a farmhouse were torn down. The state says that doesn't count, and it uses the city's own paperwork to make the point: "The City's own 2026 report to the State says construction began in 2026." The suit says there is no vertical construction and that "ground cleared in the past has gone back to weeds."

Tearing down a barn is not building a resort. If a barn demolition can start the two-year clock, the deadline means nothing. That's the question a judge will now decide.

Commerce had already ordered draw approvals stopped before it filed. According to the suit, Derby asked the state to rescind that order, and the developers asked the city to start paying again.

Follow the money

The city's own numbers, posted Nov. 13:

  • $32.25 million of Derby Shores costs are eligible for STAR bond money.
  • $9.253 million has been paid out "for work completed."
  • $22.997 million is still sitting in escrow.
  • The city claims close to $100 million in private investment. That figure hasn't been independently verified.

The announced price tag grew from $130 million to $160 million after Steven, who founded Genesis Health Clubs, came on in 2024 as "component developer" and doubled the lagoon to 4½ acres. "I didn't think it would be enough of a draw," he told the Eagle that year.

Derby says its STAR district is "performing well," its bonds "are not at risk of default," and annual audits have found no problems with how proceeds were paid out. That may all be true. It doesn't answer the basic question: what did $9.25 million in public money buy, and why is a lagoon promised for 2024 still a field?

Rick Worner's track record

Some readers may know him as "Rick Warner," but state and city records spell it Worner. He is the Leawood-area dealmaker (National Realty Advisors) behind Derby's STAR district, and his track record deserves a look.

  • Field Station: Dinosaurs, Derby. Worner pitched the district to Derby's council in 2015, with the dinosaur park as its anchor. The park opened in 2018. By 2019 it was drawing about 45,000 visitors a year against the 112,000 projected in its feasibility study, according to The Sentinel. Its $20.465 million in bonds are paid off, but the Eagle reports the park is now in danger of closing.
  • K-96 and Greenwich, Wichita. Worner was a principal of Wichita Destination Developers, the master developer of that STAR district. In March 2017, GoodSports Village Wichita sued the company, the City of Wichita and WSF Holdings in Sedgwick County (Case No. 2017-CV-00721). GoodSports alleged it was used to win state STAR approval, then pushed to buy out the developer's 20% stake for $5 million (a "fee" it called illegal) and removed when it refused. The claims included breach of contract, fraud and breach of fiduciary duty. These were allegations. The city said GoodSports was terminated for failing to meet its deadlines, and a federal court later heard sworn testimony that the GoodSports entities "never had real assets." A February 2019 federal ruling said the Wichita case "remains pending." I found no public record of how it ended.
  • Goddard. Worner's team held the city agreement for the Goddard natatorium STAR project before Steven's Goddard Sports LLC took it over.
  • One North, North Kansas City, Mo. He was the developer of a $155 million mixed-use plan backed by tax increment financing.

Worner also says he helped spearhead Kansas Speedway, Village West and Schlitterbahn. I could not independently confirm his role in those.

Worner has not been charged with any crime. I found no bankruptcy, lien or bond default tied to him. None of the developers returned the Eagle's calls.

Why Topeka should care

STAR bonds aren't a Derby problem. They're a Kansas problem. The sales tax that pays them off "would otherwise go to the State General Fund," as Commerce's own suit says. "Kansas taxpayers carry most of that cost." That's your money, whether you live in Derby, Garden City or Topeka.

In 2021, the Legislative Post Audit found only 3 of 16 STAR attractions met Commerce's tourism goals. The Legislature extended the program this year anyway. Topeka has its own STAR history: the state's database lists $10.4 million for Heartland Park.

There's one more lesson for Topeka. Whether it's STAR bonds in Derby or the TIF, CID and consultant deals at Topeka City Hall, the pattern is the same: big promises, public money out the door, and the public told to trust the paperwork. I credit Commerce for finally enforcing a deadline the Legislature wrote. Every city council in Kansas should be asking the same thing: what did the public get for the money, and when?

Questions that need answers

  1. What's the case number, and when is the first hearing?
  2. Who received the $9.253 million, and for what work? Derby's draw records are public, and I intend to ask for them under KORA.
  3. Did any developer collect fees out of STAR proceeds?
  4. Why does Commerce's database show $38,285,000 "remaining" on a $35,285,000 bond issue?

Rick Worner, Dave Murfin, Rodney Steven II and the City of Derby are welcome to respond, and I'll run it.


Sources: The Wichita Eagle, Nov. 12, 2026 (kansas.com/news/business/biz-columns-blogs/carrie-rengers/article318035193.html); KAKE, Nov. 13, 2026; KWCH, Nov. 13, 2026; City of Derby update, Nov. 13, 2026 (derbyks.gov/m/newsflash/Home/Detail/2842); Kansas Commerce STAR bond transparency database; Wichita Eagle, Apr. 4, 2017 (GoodSports suit); U.S. District Court for Kansas, Wichita Destination Developers v. Focus Hospitality Services, No. 18-2345-KHV (Feb. 5, 2019); The Sentinel, Oct. 31, 2019; Kansas Legislative Post Audit, Aug. 2021.


Henry McClure, MCRE Media | (762) 291-2765



Butt sore

Unnecessary Local Barriers Are Costing Topeka Growth

Kansas law does not require a "but-for" test for TIF, CID, or RHID projects. The state statutes set the framework. Cities may add their own policies, but they are not obligated to. Topeka chose to create an extra layer, and that choice has real consequences.

The but-for standard asks whether a project would happen without public assistance. In report R-24-012, the Kansas Legislative Division of Post Audit described this as an inherently unknowable question. It depends on private business decisions that cannot be fully observed or predicted. Academic research on incentives, including work by Timothy Bartik of the Upjohn Institute, finds that typical but-for percentages fall in a low range, often 2 to 25 percent. In most cases the project would have gone ahead anyway. A local requirement that forces developers to prove the unknowable simply adds cost, time, and uncertainty.

Some will point out that the auditors did not recommend eliminating the test. They didn't have to. They told us the question can't be answered, and what to do with that finding is up to the Governing Body.

Topeka's local policy applies this test to private applicants. In practice it has used return benchmarks, such as the roughly 8.5 percent capitalization rate in recent reviews, and it relies on outside analysis, often from Columbia Capital Management and Jeff White. Private developers pay application and funding fees that have gone up, plus the cost of consultant review. The public record has not shown the same standard applied with equal rigor to projects involving the City or GO Topeka.

Municipal advisory services are available from many firms, and fees are negotiable. When one firm becomes the default reviewer for an extra local test the state does not require, the process itself generates revenue for consultants while raising the hurdle for the private sector. Each added fee, study, and approval step raises the total cost of a project. Higher costs mean fewer projects get finished. Fewer projects mean less private capital, fewer jobs, a smaller tax base, and slower growth.

Free enterprise responds to the conditions it actually faces. When cities lower unnecessary barriers with streamlined approvals, fewer subjective tests, and competitive professional fees, private investment increases. Capital is mobile, and developers and businesses compare locations. Places that treat the private sector as a partner rather than a source of fees and process tend to attract more activity. Places that layer local rules on top of state law and then route the analysis through preferred consultants tend to grow more slowly.

The Governor and the Department of Commerce operate under the statutes the Legislature wrote. Those statutes do not impose the but-for requirement Topeka adopted. Local officials who add it are choosing a stricter standard than the one the state itself uses. That is a policy decision, not a legal mandate, and the Governing Body can reverse it.

A straightforward change would bring Topeka in line with state law:

- Retire the local but-for requirement for private TIF, CID, and RHID applications, or apply any remaining review uniformly and transparently to every project, including those involving public entities.
- Publish the amounts paid to outside advisors for incentive analysis.
- Limit fees to actual, competitive costs rather than an open-ended process.

The result is lower friction, clearer rules, and a signal that private capital is welcome.

Growth in a free-market economy comes from people willing to risk their own money on projects that create value. Extra local tests, premium consultant fees, and uneven application of the rules make that risk higher and the return less certain. Removing obstacles the state does not require is one of the clearest, lowest-cost steps Topeka can take to compete. The Governing Body can make that change, and the evidence supports doing so.

*Henry McClure, MCRE, LLC · (762) 291-2765*



Henry McClure
785.383.9994 

Sent from my T-Mobile 5G Device
Get Outlook for Android

The father in law stuff is really concerning

**Braxton Bragg Copley** is a longtime City of Topeka official (Deputy City Manager, retiring January 4, 2027) whose public record centers on legal, utilities, public works, and development roles, a multi-year private-sector interval tied to Pioneer Group-related entities, and project management of the Hotel Topeka acquisition and sale.

### Education and Credentials
- Bachelor’s degree, Colorado College (1985).
- Juris Doctor, University of Kansas School of Law (1992); admitted to practice in Kansas that year.
- High school: Air Academy High School (per social media profiles).
- Holds multiple technical certifications in water treatment, cross-connection control, and temporary traffic control (cited in city announcements).
- Martindale peer rating of 4.4 (municipal law).

### City of Topeka Career Timeline (Public Sources)
Copley has roughly 21+ years of service with the city, with a gap from late 2012 to 2017:

- September 2000: Joined City Attorney’s office.
- 2002: Assistant City Attorney.
- January–August 2008: Interim City Attorney (before Jackie Williams was named permanent).
- February 2011: Utilities & Transportation Director.
- December 14, 2012: Left for private sector.
- April 2017: Returned as Deputy Utilities Director.
- 2020: Interim Utilities Director (after Bob Sample’s retirement); 2021: permanent Utilities Director.
- October 2022: Public Works Director (after also serving as interim).
- August 2024: Assistant City Manager (infrastructure and development portfolio); later elevated to Deputy City Manager in the same area.
- Served briefly as acting/interim City Manager after Robert Perez’s October 2026 resignation (until an outside interim was installed).
- Retirement effective January 4, 2027. City statements credit him with oversight of Public Works, Utilities, capital improvement planning, transportation, stormwater, and related infrastructure projects. He also held Economic Development and Planning director roles at points.

Compensation (OpenTheBooks / public payroll data): Assistant City Manager ~$177,721 (2024); Deputy City Manager ~$226,792 (2025). Earlier Utilities Director salary was reported at $130,000 (2021).

### Private-Sector Interval and Pioneer Connection (2012–2017)
After leaving city employment in December 2012, Copley formed multiple LLCs using the address 1200 S Kansas Ave, Topeka, KS 66612 (the address associated with Ross R. Freeman’s Pioneer Group, Inc.):

- Pioneer Historic Investment, LLC (formed March 14, 2013; Copley as registered agent; still listed as active).
- Other entities include Pioneer Investment Bulldog, LLC; Pioneer Investment Ridge Top II, LLC; TB Investment, LLC; and related filings.

Pioneer Group (founded by Freeman in 1997) specialized in historic rehabilitation and affordable housing using historic tax credits, LIHTC, and local incentives such as Neighborhood Revitalization Program rebates. Public records place Copley’s LLCs at the same address during the private-sector period. Freeman was Copley’s father-in-law (as referenced in prior local discussion). No public records detail specific deal outcomes or compensation from these entities.

### Hotel Topeka Role
Copley served as project manager for the Topeka Development Corporation’s acquisition and later disposition of Hotel Topeka (1717 SW Topeka Blvd.):

- City/TDC acquired the distressed property in 2023 for roughly $7.6–8.6 million.
- City invested additional millions in operations, maintenance, and a ~$554,000 consultant engagement (REVPAR International). Total city outlay has been reported in the $12–14+ million range (figures vary by source and date).
- Occupancy and operating performance under city management fell short of projections; annual operating losses were cited around $1.75 million in some periods.
- December 2025/early 2026: TDC approved sale to Wichita-based Endeavor Hotel Group for $1 million cash (plus earnest money), with Endeavor committing ~$6 million in renovations plus working capital. The structure is designed so the city recovers the remaining ~$11–12 million over time via a new 2% Community Improvement District (CID) sales tax and incremental Transient Guest Tax (TGT) captures, estimated at 20+ years.
- Copley presented budgets, signed off on consultant work, negotiated terms, and advocated the self-management approach followed by the eventual structured sale. City statements describe the deal as balancing recovery of investment against the buyer’s capital commitment and risk.

Critics (including local commentary) have characterized the net taxpayer exposure as large and the self-management phase as costly; official city materials frame it as a necessary step that produced a private operator and a long-term recovery mechanism.

### Other Notes from Public Records
- No criminal records associated with the name Braxton Copley appear in available public databases.
- After Perez’s 2026 resignation, Copley briefly served in an acting capacity while the city hired an external interim manager.
- City communications consistently describe him as a long-serving internal leader with deep institutional knowledge of infrastructure and development functions.

This is the documented public record drawn from city announcements, news reporting, payroll data, business filings, and TDC materials. Primary sources include Topeka Capital-Journal and WIBW coverage of the retirement and Hotel Topeka sale, OpenTheBooks salary data, Kansas business entity filings, and city press releases.

Henry McClure
785.383.9994 

Sent from my T-Mobile 5G Device
Get Outlook for Android

The X-Files: Tuesday, Nov 17, 2026

Source: @KCStar posts since yesterday morning.

Real estate

Local news, crime & courts

Politics

Chiefs, Royals & sports

Business

Food & culture

Good morning

**City of Topeka Planning Commission Meeting — November 16, 2026**

This is the full video recording of the regular Planning Commission meeting held at 6:00 p.m. in the City Council Chambers (214 East 8th Street).

### Agenda Summary
- **Roll call**
- **Approval of minutes** from the October 19, 2026 meeting
- **Declaration of conflicts of interest / ex parte communications**

**Action Item**
- **CPA26/02 – Land Use & Growth Management Plan 2040 Update**  
  Updates to the City’s comprehensive land use and growth plan. Changes reflect how the plan has been implemented since its 2015 adoption, incorporate related plans (including the Citywide Housing Study and Strategy), update density references for consistency with recent zoning amendments, encourage adaptive reuse of vacant or underutilized commercial properties for multifamily residential, and include recommended revisions to the Future Land Use Map.

**Discussion Items**
- **ACZR26/03 – Parking Regulations Update**  
  Substantial rewrite of the Off-Street Parking Regulations (Chapter 18.240 of the Zoning Code). Goals include preventing adverse effects of insufficient parking, maintaining public safety and reducing congestion, while also lowering unnecessary barriers to development and allowing more flexibility based on context and specific circumstances.

- **CPA26/03 – East Topeka South Neighborhood Plan**  
  Update to the neighborhood plan covering the area bounded by SE 6th Avenue (north), SE Branner Street (west), SE Deer Creek Parkway (east), and I-70 (south).

**Other**
- Report from the Special Committee on Housing
- General public comment
- Communications to the Commission
- Adjournment

The meeting focuses on comprehensive plan housekeeping, parking code modernization, and a neighborhood plan revision—core topics for local land use and development in Topeka. Official minutes with votes and detailed discussion are not yet published (the video was just posted). The full agenda packet is available on Topeka Speaks.

Henry McClure
785.383.9994 

Sent from my T-Mobile 5G Device
Get Outlook for Android

Four Years, $35 Million in Bonds, No Lagoon: The State Sues Over Derby Shores

By Henry McClure, MCRE Media | Nov. 16, 2026 Picture a 4½-acre crystal-blue lagoon with a hotel, apartments, a tiki bar, a zipline and water...