2.0 ATT building - WASTE of Tax Dollars

GO Topeka Innovation Center Cost Breakdown
Project Location: 220 SE 6th St, Topeka, KS 66603
Date of Estimate: November 26, 2024
Source: KBS Constructors, Inc. - Scope Narrative (Attachment #1)
Initial Buildout CostsThe initial buildout includes the core tenant improvements, mechanical equipment, restrooms, lab buildout, hoods, innovative suites, and the pitch room.
Scope
Total w/o Tax
Add for Tax
Total w/ Tax
Notes
Tenant Buildout
$4,590,640
$428,754
$5,019,394
Includes design services
Mechanical Equipment/Vertical Rough-In
$592,653
$48,112
$640,765
Restrooms
$91,054
$7,147
$98,201
Lab Build Out Unit Price
$86,417
$5,478
$91,895
Per unit price
Hood Unit Price
$142,305
$12,858
$155,163
Per unit price
Innovative Suite Build Out Unit Price
$21,704
$1,965
$23,669
Per unit price
Sub-Total
$5,524,773
$504,314
$6,029,087
Pitch Room
$440,509
$38,256
$478,765
Initial Buildout Total
$5,965,281
$542,571
$6,507,852
All-In Scenario CostsThe all-in scenario assumes additional lab buildouts, hoods, and innovative suites are constructed concurrently with the initial buildout.
Scope
Total w/o Tax
Add for Tax
Total w/ Tax
Notes
Initial Buildout Total
$5,965,281
$542,571
$6,507,852
As above
Add Lab Build Out (5 units)
$345,667
$21,913
$367,580
5 labs at unit price
Add Hoods (3 units)
$284,610
$25,716
$310,326
3 hoods at unit price
Add Innovative Suite Build Out (3 units)
$43,408
$3,930
$47,338
3 suites at unit price
All-In Scenario Total
$6,638,966
$594,130
$7,233,096
Assumes concurrent work
Key Notes
  1. Contingencies:
    • 5% Construction Contingency included.
    • 5% Design Contingency included.
  2. Permit Fees: Anticipated City of Topeka permit fees are included.
  3. Scope Details: For specific inclusions and exclusions, refer to the Scope Narrative (Pages 41–45).
  4. Tax: Costs include applicable taxes as noted in the breakdown.
  5. Design Services: Tenant buildout cost includes architectural, structural, and MEP engineering services through schematic design, design development, construction documents, and construction administration.
  6. Assumptions: The all-in scenario assumes work is performed concurrently with the initial buildout to optimize scheduling and costs.
Scope Highlights
  • Tenant Buildout: Includes demolition, concrete work, steel structures, carpentry, doors, glazing, drywall, flooring, painting, fire sprinklers, plumbing, mechanical, electrical, and furnishings (e.g., casework, reception desk, appliances).
  • Mechanical Equipment/Vertical Rough-In: Includes ductwork, exhaust systems, RO water system, and VRF heating/cooling.
  • Restrooms: Includes finishes, fixtures, and accessories.
  • Lab Build Out: Includes casework, workstations, countertops, and mechanical connections.
  • Hoods: Includes 6' lab hoods with auto sash and exhaust systems.
  • Innovative Suite Build Out: Includes furnishings for cubicles, conference tables, and printer spaces.
  • Pitch Room: Includes carpentry, finishes, furnishings, fire sprinklers, plumbing, mechanical, electrical, and audio-visual systems.

This summary provides a high-level overview of the project costs for the GO Topeka Innovation Center. For detailed scope descriptions, refer to the Scope Narrative (Pages 41–45). If you need further analysis or specific details (e.g., breakdown by trade or additional clarifications), please let me know!


--
Henry McClure 
Time kills deals
785-383-9994

www.henrymcclure.live

Sunday, July 13, 2025

Fwd: Rolling Meadows Neighborhood Association on Monday, July 21 at 6:30 p.m.



Henry McClure  
785.383.9994
sent from mobile 📱
time kills deals

---------- Forwarded message ---------
From: judyw1017@aol.com <judyw1017@aol.com>
Date: Sat, Jun 28, 2025, 1:47 PM
Subject: Rolling Meadows Neighborhood Association on Monday, July 21 at 6:30 p.m.
To:


The Rolling Meadows Neighborhood Association would like to invite you to participate in the Mayoral Candidate Forum during the monthly meeting on Monday, July 21 at 6:30 p.m.  The location will be provided at a later date.  Please let me know by July 4 if you would like to participate in the Forum.

Thank you

Judy Wilson
Secretary
Rolling Meadows Neighborhood Association


Re: Rolling Meadows Neighborhood Association on Monday, July 21 at 6:30 p.m.

I plan to attend.

Henry McClure  
785.383.9994
sent from mobile 📱
time kills deals

On Sun, Jul 13, 2025, 10:05 PM judyw1017@aol.com <judyw1017@aol.com> wrote:

Henry,

The Rolling Meadows Neighborhood Association will meet on Monday, July 21 at 6:30 p.m. The program will be a Mayoral Candidate Forum for the candidates for Mayor.

Our meeting will be at 3800 SE Michigan, the building that used to be owned by American Legion Post One. Currently the building is being used by the Iglesia Casa De Dios Topeka church.  

Each candidate will have 5 minutes to talk about themselves including why they want to be the mayor.  Questions will be asked of each candidate and there will be time for questions and answers after all candidates have spoken.

Please let me know if you have questions.

Thanks
Judy

On Saturday, June 28, 2025 at 03:11:18 PM CDT, Henry McClure <mcre13@gmail.com> wrote:


Yes 

Henry McClure  
785.383.9994
sent from mobile 📱
time kills deals

On Sat, Jun 28, 2025, 1:47 PM judyw1017@aol.com <judyw1017@aol.com> wrote:
The Rolling Meadows Neighborhood Association would like to invite you to participate in the Mayoral Candidate Forum during the monthly meeting on Monday, July 21 at 6:30 p.m.  The location will be provided at a later date.  Please let me know by July 4 if you would like to participate in the Forum.

Thank you

Judy Wilson
Secretary
Rolling Meadows Neighborhood Association


Saturday, July 12, 2025

From a voter

The Capital Journal article on the mayor forum portrayed you positively, though it was reduced to soundbites. Sean and I have concerns about illegally placed Duncan for mayor signs, which are too early, too close to streets, and on public property, suggesting they should be removed. As your unofficial advisor, I recommend focusing on waste, fraud, abuse, and the "good old boy" network, as these resonate with voters. Key issues include the hotel, tax foreclosure on the race track, JEDO/Chamber/Go Topeka, and the AT&T building, though the latter may be tricky due to visible construction. I'll promote your success in bringing quality businesses to Topeka and your commercial realty projects to avoid self-promotion. Continue attending public events like those at Evergy Plaza and leverage NOTO's popularity. Your property listings are a smart promotional tool. Grassroots efforts like yard signs and door-to-door campaigning, as you did for the City Council, are effective. You're connecting well with lower-income voters, who dislike good old boy projects and lack of entertainment like the race track. Consider hosting a local music event or focusing on historical community ties (e.g., McClure Street, Colmery Hospital) to appeal to older voters. Visiting retirement communities can also score points. My background in Kansas politics—through my mom's legislative work, my dad's hospital lobbying, and my own experience as a young lobbyist and campaign volunteer—gives me insight, though it's dated. I was active on Free Republic and CJ Online as AdAstra, and now stir debate on Facebook, though I avoid political posts on my own feed, focusing on personal content.

Henry McClure  
785.383.9994
sent from mobile 📱
time kills deals
https://www.facebook.com/share/r/1EgnEbVJT4/?mibextid=D5vuiz

Henry McClure  
785.383.9994
sent from mobile 📱
time kills deals